Did the CRMC mislead the public about their authority regarding National Grid’s proposed liquefaction...

The Rhode Island Attorney General's Office recently determined that the Rhode Island Coastal Resources Management Council (CRMC) improperly denied the APRA (Access to Public...

EFSB hears opening statements on proposed Invenergy power plant

Today the Energy Facilities Siting Board (EFSB) heard opening statements as the final hearings to determine whether or not Invenergy will build a $1...

CLF’s Jerry Elmer asks, “How stupid does Invenergy think the people of Rhode Island...

"In other words, while it is true that Invenergy could file a similar complaint in the future, Invenergy will not be doing so," asserted...

A busy week in the Invenergy case

This has been a busy week in the Invenergy case, culminating in a Federal Energy regulatory Commission (FERC) ruling on Friday late afternoon in...

Invenergy still trying to shift costs onto consumers maintains CLF and Burrillville, new Show...

In response to the cancellation of next week's Show Cause Hearing, lawyers from Conservation Law Foundation (CLF) and the Town of Burrillville are asking...

EFSB cancels Invenergy show cause hearing

Rather than defend their actions before the Energy Facility Siting Board (EFSB) at a January 30 "show cause" hearing and risk having their application...

Invenergy withdraws one of two FERC lawsuits

Invenergy continues to clean up its messes. In a letter, Invenergy writes, "because the lawsuit has "proven contentious in the Rhode Island Energy Facility Siting...

Invenergy: Not Ready for Prime Time!

Here is a mildly amusing sidelight to the Invenergy saga. Invenergy’s ham-fisted missteps might be funny if there were not so much at stake. Invenergy seems...

CLF’s Jerry Elmer: ‘Invenergy is being a bully.’

"As a public relations matter, this makes Invenergy look like a bully," said Conservation Law Foundation (CLF) Senior Attorney Jerry Elmer referring to the...

Invenergy: Delays in permitting power plant due to uninformed opposition, not our incompetence

Invenergy has sent a letter to the Federal Energy Regulatory Commission (FERC), claiming that delays in the permitting process before the Rhode Island Energy...