New testimony in the Invenergy hearings currently before the Energy Facilities Siting Board (EFSB) was filed today on whether or not the electricity from the proposed $1 billion racked gas and diesel oil burning power plant aimed at the pristine forests of Burrillville is needed by ISO-NE, the operator of the New England electricity grid.
See also: Without a power plant, Invenergy is making millions off New England ratepayers
Conservation Law Foundation (CLF) filed a Memorandum from their expert witness Robert Fagan based on new information that "has become available since February 2018 concerning any purported need for either unit 1 (485 MW) or unit 2 (485 MW) of Invenergy’s proposed Burrillville power plant. These units are sometimes referred to as 'Turbine One' and 'Turbine Two.'” Fagan (page 1-4) tells a very simple story: the electricity from Invenergy's proposed power plant is not needed in New England. Fagan bases his analysis on four major points:
UpriseRI is entirely supported by donations and advertising. Every little bit helps: Become a Patron!
See also: Without a power plant, Invenergy is making millions off New England ratepayers
Conservation Law Foundation (CLF) filed a Memorandum from their expert witness Robert Fagan based on new information that "has become available since February 2018 concerning any purported need for either unit 1 (485 MW) or unit 2 (485 MW) of Invenergy’s proposed Burrillville power plant. These units are sometimes referred to as 'Turbine One' and 'Turbine Two.'” Fagan (page 1-4) tells a very simple story: the electricity from Invenergy's proposed power plant is not needed in New England. Fagan bases his analysis on four major points:
- There is a current surplus of generating capacity in New England; while
- Peak load, which drives future demand, is declining; while
- The pace of retirements of existing power plants shows no need for new power plants; while
- Large procurements of new renewables are coming into the New England electricity market.
- FERC’s recent approval of the ISO’s newly lowered Dynamic De-List Bid Threshold (pages 4-5);
- the ISO’s newly released 2018 CELT Report showing consistently decreased demand (CELT = Capacity, Energy, Loads and Transmission) (pages 5-6);
- the recently announced retention of Mystic Units 8 and 9 (page 8-9);
- and the recently-announced new procurements of Canadian hydro power and offshore wind by Rhode Island, Massachusetts, and Connecticut (pages 9-11).