Two Years of Steel Plates: North Providence Council Orders Brook Farm Bridge Design After Residents Push Back

Two years after temporary steel plates went down on the Brook Farm Road Bridge, North Providence still has no structural design, no survey and no engineer assigned. Residents pressed the council Tuesday, and it voted to start a conceptual design rather than wait on federal grant money.

A hand-drawn editorial sketch of the corner of a heavy steel road plate lying over asphalt, seen extremely close from just above pavement level so…
Why This Matters

Drivers using the Brook Farm Road Bridge will keep crossing temporary rented steel plates for the foreseeable future. The council asked the mayor to begin a conceptual design and collect price quotes, and asked DPW to clean around the barriers. A federal funding decision is estimated at two to three months out.

The North Providence Town Council voted Tuesday to ask the mayor's office to begin a conceptual design and gather price quotes for repairs to the Brook Farm Road Bridge, which has carried temporary steel plates for about two years.

The vote came by voice vote at the council's August 4 meeting, according to the town's published meeting recording, after two residents of the same household delivered extended criticism of the pace of the work. One council member recused himself from the item before discussion began; the chair noted the recusal for the record.

A conceptual design is an early-stage engineering sketch that establishes what a fix would look like and roughly what it would cost. It is not construction, and it does not commit the town to a contractor. What the council approved was a letter to the mayor asking that the work begin and that quotes be collected, rather than waiting for grant money to arrive first.

Local sponsorAffordable photography lessons in Newport, Jamestown, or your town.E.L. Photo RI

What residents said

A resident who told the council he lives on Carriageway said he had raised the bridge with the council roughly four months earlier and had seen nothing tangible happen since. He said the temporary plates over the bridge have been in place for what he believes is now two years.

"Those plates aren't going to last. That's not a permanent fix, right?" he said, adding that he assumed the plates were installed for a safety reason. He said he had spoken about a month earlier with the town's retained engineer, who told him the project would be expensive and that permitting alone could reach six figures.

The resident, who said his company does civil engineering work, argued the town should be soliciting ideas and prices now. He described a project his firm is involved with in which a structural engineer designed an insert to reinforce an aging culvert rather than rebuild it, and suggested a comparable approach might be worth pricing here.

"I think you got to go out to bid and get some ideas of prices, I would assume, before you can come up with a solution and find out what it's going to cost," he said. "Because right now I don't think anybody knows how much it's going to cost to replace that."

He also raised the cost of the plates themselves. He said he did not believe the town owns them, and that a rental payment has presumably been running for two years. Asked directly during the discussion whether the town rents the plates, an official confirmed that it does. The transcript does not include a rental figure, and the recording does not make clear which company supplies them.

A second resident from the same address addressed the council afterward, holding up images of the bridge. She said the town's Department of Public Works is not keeping the bridge clear of debris and described garbage along both sides. She said the condition does not match what residents pay, noting North Providence's tax rate and home values in her plat. She also said the plated section functions as "a giant speed bump," and that vehicles take a hit going in and out.

She asked the council for a figure on what the plate rental is costing, and said she intends to come back for an answer.

What the town said

The town's grants manager told the council the bridge was flagged as a priority when she started, and that she applied for an earmark grant, a congressionally directed federal award. She said that process can take about a year for approval and longer to obligate — meaning the money is not usable until a detailed final application and budget are submitted.

Because the town already holds an earmark for a nearby parkway project, she said, staff are pursuing a "technical correction," a change of scope that would let the existing federal money be redirected to the Brook Farm Road Bridge and to broader stormwater work in the area. She said the U.S. Environmental Protection Agency indicated the change is allowed, that discussions are moving in the right direction, and that the town may also be exempt from environmental review and any local match requirement.

She cautioned against getting ahead of the process. She said the correction could take another two or three months, and that she could not speak to it as settled. Asked whether the town has a plan for the bridge itself, she said options are still being discussed and that a structural design would have to be bid out if the correction is approved.

Mayor Charles A. Lombardi told the council the bridge is safe. He said the open question is whether a replacement span would be built on site or fabricated off site in a welding yard and dropped into place, which he said would shorten the road closure. He said the last estimate he was given was somewhere around $600,000 to $700,000, which he called hard to believe given the bridge's size. If the fund transfer does not go through, he said, the administration would come back to the council to ask for the money.

The first resident said he took the mayor at his word on other matters but was not persuaded on safety. "You're telling me it's safe, but there's a reason why those plates are there. It must not be safe. That's my opinion," he said. An official responded that the plates were installed to make the crossing safer than what was there.

The resident said his understanding is that substandard concrete was used in the original construction, and he noted the problem predates the current administration. His central point was procedural: there is no structural engineer assigned, no survey performed, and no design underway, so even if grant money lands, the town would be starting from zero.

"Let's try and get that going a little bit forward," he said. "It's not a lot of money, I don't think, to do that."

A council member then moved to send a letter to the mayor to begin a conceptual design and start getting quotes. The motion was seconded and approved by voice vote.

One council member said the problem should have been addressed from day one, when the structural cause should have been identified, and said the town had instead kicked the can down the road as it had with another bridge.

The council took a second action on the item: a separate motion, also approved by voice vote, asking the Department of Public Works to clean around the barriers at the bridge and to continue maintaining the area. That is the piece residents may see first, and it does not require any grant.

What happens next

There is no date attached to the conceptual design work, and the recording does not indicate when the letter would go out or when the council expects a response. The grants manager's estimate of two to three months on the federal technical correction would put a decision in the fall. Until then, the plates stay, and the rental cost — a number no one on the recording produced — keeps running.

Residents seeking the plate rental figure, or an update on the design request, can raise the item at a future regular council meeting. The council's discussion of the bridge, including the vote, is available in the town's published recording of the August 4 meeting.